Appendix 1: Self-Test Answer Keys
Competency D1
Self-Test 1
- b. SCFM is standardized using 14.7 psia (103 kPa ab)
 - d. Different sizes and assembled in series
 - b. Double acting
 - d. Intercooler
 - b. Reciprocating diaphragm
 - b. Reciprocating diaphragm
 - d. Rotary helical screw
 - e. Rotary scroll
 - d. Intake air filter
 - a. Downstream of the aftercooler
 - a. Downstream of the compressor
 - c. Air cooling and water cooling
 - b. It improves compressor efficiency.
 - b. It causes excessive compressor cycling.
 - a. It wastes energy because the compressor has to run longer.
 - d. Salt tablets
 - b. It provides additional protection from contamination.
 - b. Place the equipment with high flow requirements near the compressor.
 - c. Closed-loop networks
 - b. Octopus networks
 - b. Zero-loss drains
 - a. Pneumatic/mechanical drains; electronic demand drains; series timed electronic drains
 - a. The oil from the lubricator could cause other components to plug and become inoperable.
 - d. Bursting disk
 - a. Fusible plug
 - b. Pressure relief valve
 
Self-Test 2
- 2 psi (14 kpa)
 - d. 50 000 BTU/hr.
 - c. Eye protection and air respirators
 - c. 70 kPa gauge (10 psig)
 - a. Insulation and heat tracing
 - c. High temperature–rated steel-braided, vibration isolation flex hose
 - d. Velocity fuse.
 - b. A quick disconnect coupling
 - a. Off the top of the main
 - d. All of the above
 - a. Possibility of corrosion when exposed to condensate
 - c. Possibility the material may shatter when pressurized
 - d. 95-5 soldered or brazed connections
 
Competency D2
Self-Test 1
- b. Ultrasonic testing
 - d. The last 9 m (30 ft.) of piping before the point of use
 - b. 20–30%
 - e. All of the above
 - a. Equipment malfunction
 - d. Discharge temperature
 
Competency D3
Self-Test 1
- b. Higher efficiency and economic gains
 - a. Reduced capacity and reduced efficiency
 - c. The condensate drains
 - b. Manual drains
 - b. 2 or 3
 - a. A clogged condenser
 - d. 8–10 psi (56 – 70 kPa)
 - d. Dusting
 - c. A 30-cm (2 ft.) whip hose
 - c. The internal orifice is the same size as the pipe size and does not have a ball or a spring.
 - d. The last 9 m (30 ft.) of piping before the point of use
 - b. 20–30%
 - b. Ultrasonic testing