Appendix 1: Self-Test Answer Keys
Competency D1
Self-Test 1
- b. SCFM is standardized using 14.7 psia (103 kPa ab)
- d. Different sizes and assembled in series
- b. Double acting
- d. Intercooler
- b. Reciprocating diaphragm
- b. Reciprocating diaphragm
- d. Rotary helical screw
- e. Rotary scroll
- d. Intake air filter
- a. Downstream of the aftercooler
- a. Downstream of the compressor
- c. Air cooling and water cooling
- b. It improves compressor efficiency.
- b. It causes excessive compressor cycling.
- a. It wastes energy because the compressor has to run longer.
- d. Salt tablets
- b. It provides additional protection from contamination.
- b. Place the equipment with high flow requirements near the compressor.
- c. Closed-loop networks
- b. Octopus networks
- b. Zero-loss drains
- a. Pneumatic/mechanical drains; electronic demand drains; series timed electronic drains
- a. The oil from the lubricator could cause other components to plug and become inoperable.
- d. Bursting disk
- a. Fusible plug
- b. Pressure relief valve
Self-Test 2
- 2 psi (14 kpa)
- d. 50 000 BTU/hr.
- c. Eye protection and air respirators
- c. 70 kPa gauge (10 psig)
- a. Insulation and heat tracing
- c. High temperature–rated steel-braided, vibration isolation flex hose
- d. Velocity fuse.
- b. A quick disconnect coupling
- a. Off the top of the main
- d. All of the above
- a. Possibility of corrosion when exposed to condensate
- c. Possibility the material may shatter when pressurized
- d. 95-5 soldered or brazed connections
Competency D2
Self-Test 1
- b. Ultrasonic testing
- d. The last 9 m (30 ft.) of piping before the point of use
- b. 20–30%
- e. All of the above
- a. Equipment malfunction
- d. Discharge temperature
Competency D3
Self-Test 1
- b. Higher efficiency and economic gains
- a. Reduced capacity and reduced efficiency
- c. The condensate drains
- b. Manual drains
- b. 2 or 3
- a. A clogged condenser
- d. 8–10 psi (56 – 70 kPa)
- d. Dusting
- c. A 30-cm (2 ft.) whip hose
- c. The internal orifice is the same size as the pipe size and does not have a ball or a spring.
- d. The last 9 m (30 ft.) of piping before the point of use
- b. 20–30%
- b. Ultrasonic testing